Case status: Findings adopted on 17.03.2021 – Non-compliance found. The Meeting of the Parties postponed the decision-making on the Findings; see Decision VI/f.
Follow-up: -
Topics: Definitions; Access to justice.
Articles alleged: 9 (3), 9 (4).
Articles considered by the Committee: 2 (2); 9 (3), 9 (4).
Articles, if any, found in non-compliance: 9 (3), 9 (4).
Summary: On 9 March 2015, non-governmental environmental organizations GLOBAL 2000 and OEKOBUERO – Alliance of the Austrian Environmental Movement submitted a communication to the Compliance Committee alleging the failure of the European Union to comply with article 9 (3) and (4) of the Convention concerning access to justice regarding the European Commission decision to approve State aid for the nuclear power plant project, Hinkley Point C.
Documents | Status | Date received or posted by the secretariat |
---|---|---|
Communication Annex 1 Annex 2 Annex 3 Annex 4 Annex 5 Annex 6 Annex 7 Annex 8 |
From the communicant | 09.03.2015 |
Additional information | From the communicants | 20.05.2015 |
Statement on preliminary admissibility | From the United Kingdom | 29.06.2015 |
Letter to Party concerned enclosing preliminary determination of admissibility and forwarding communication for Party concerned's response | From the secretariat | 05.10.2015 |
Email sending letter to Party concerned enclosing preliminary determination on admissibility and re-forwarding communication for its response | From the secretariat | 22.12.2015 |
Response to communication | From the Party concerned | 20.05.2016 |
Statement |
From observer (Friends of the Earth England, Wales & Northern Ireland) | 19.07.2016 |
Comments in response to Party concerned's response to communication dated 20.05.2016 | From the communicants | 07.09.2016 |
Letter to the parties seeking their views on whether a hearing is needed | From the secretariat | 18.11.2016 |
Reply to secretariat's letter | From the communicants | 24.11.2016 |
Reply to secretariat's letter | From the Party concerned | 28.11.2016 |
Letters inviting Party concerned and communicants to hearing at Committee's 60th meeting | From the secretariat | 29.01.2018 |
Update | From the communicant | 26.02.2018 |
Opening Statement for the hearing at the Committee's 60th meeting | From the communicant | 14.03.2018 |
Opening Statement for the hearing at the Committee's 60th meeting | From the Party concerned | 15.03.2018 |
Questions from the Committee to the Party concerned | From the secretariat | 26.03.2018 |
Request for an extension to reply to the Committee's questions | From the Party concerned | 09.04.2018 |
Decision of the Chair of the Committee to grant an extension | From the secretariat | 13.04.2018 |
Request for extension to comment on Party's reply to Committee's questions | From the communicant | 03.05.2018 |
Decision of Chair to grant an extension to communicant | From the secretariat | 04.05.2018 |
Reply to the Committee's questions of 26.03.2018 | From the Party concerned | 26.06.2018 |
Annex to reply to Committee's questions of 26.03.2018 | From the Party concerned | 02.07.2018 |
Comments on Party concerned's reply of 26.06.2018 to Committee's questions | From observer (Client Earth) | 20.07.2018 |
Comments on Party concerned's reply of 26.06.2018 to Committee's questions | From the communicant | 21.07.2018 |
Comments on the communicant's comments of 21.07.2018 | From the Party concerned | 26.10.2018 |
Comments on the Party concerned's comments of 26 October 2018 | From observer (ClientEarth) | 01.02.2019 |
Statement | From the communicants and observer (ClientEarth) | 12.03.2020 |
Email enclosing update letter Annex: CJEU judgment C-594/18 P 22.09.2020 |
From the communicant Okoburo and the observer ClientEarth | 06.11.2020 |
Email inviting Party concerned to comment on the CJEU’s judgment in C 594/18 P Austria v. Commission | From the secretariat | 23.11.2020 |
Comments on the communicant’s and observer’s update of 06.11.2020 | From the Party concerned | 07.12.2020 |
Draft findings and letters to the Party concerned and communicants inviting their comments | From the secretariat | 18.01.2021 |
Comments on the Committee's draft findings | From the Party concerned | 24.02.2021 |
Comments on the Committee’s draft findings | From observer (ClientEarth) | 01.03.2021 |
Comments on the Committee's draft findings | From the communicant (OEKOBUERO) | 01.03.2021 |
Findings ENG FRE RUS | 17.03.2021 |