Skip to main content

E255: Strengthening statistical capacity for producing comparable and reliable poverty indicators for monitoring of the sustainable development in the CIS countries

EXCOM Form:

 

EXCOM form

Concept Paper or Project Document:

 

Project doc, including the budget

Annual Progress Reports:

 

Annual funds utilization report 2016

Final Report:

 

 

Key project deliverables:

 

 

Links to project page:

 

 

Evaluation:

 

https://unece.org/evaluation-reports

 

Implementation

 

 
Part I. Planning
(to be filled in before submission to EXCOM)
Part II. Implementation
(to be used for reporting on progress in the implementation of the project in real time)1,2

Expected accomplishments

Planned activities

Estimated costs (US$)

Implemented activities3

Actual expenditures4 (US$)3

EA 1:Strengthened capacity of national statistical offices of CIS countries to produce poverty statistics

A1.1 Workshop on the practices of poverty measurement

45 200

 

Workshop on poverty measurement, Geneva, 11 July 2016. List of participants

 

A1.2 Workshop on harmonizing the sources and methods of poverty measurement

56 500

High-level Seminar on Harmonisation of Poverty Statistics in CIS Countries, Sochi (Russian Federation), 31 October - 2 November 2016. List of participants

 
       

EA 2: Increased harmonization of poverty statistics in CIS countries

A2.1 Development and testing of model survey questions

22 600

Analysis of household survey questionnaires: ToR, report

Model survey questions: ToR

 

A2.2 Development of technical guidelines

22 600 Model survey questions: ToR  
  A2.3 Workshop for reviewing the test results and the draft guidelines 56 500  
Total: 203 400 Total:  
Footnote


1 The secretariat shall inform EXCOM in case of unexpected developments or serious problems of any kind in the project implementation.
2 Questions from member States on project implementation will be forwarded to the secretariat.
Relevant information should be uploaded by the project manager on the Project Monitoring Tool within one month from the end of the activity and include the following:
(a) For an advisory service (including at a workshop/seminar/training organized by other organizations): title; venue; dates; project expenditures; and hyperlink(s) to presentation(s) and other relevant documents;
(b) For a workshop/conference/training organized by UNECE: title; venue; dates; project expenditures; and hyperlinks to the meeting agenda, list of participants, presentation(s) made by UNECE, conference documents, training materials and reports;
(c) For a consultancy: project expenditures; hyperlinks to the consultancy ToR and main outputs (study, report, training material, presentation, etc.) produced by the consultant/s;
(d) For other outputs not included under bullet points above: hyperlink to relevant documents.  
[1] Relevant financial information – certified by the Executive Office - should be uploaded by the project manager on the Project Monitoring Tool within one month from the end of the activity.

 

Go back to the list of projects for Statistics
Go back to the main list of projects