E210: UNECE Gas Centre Programme

EXCOM Form:

 

EXCOM form

Concept Paper or Project Document:

 

Concept paper / TOR

Project doc, including the budget

Work/implementation plan

Annual Progress Reports:

 

 

Final Report:

 

 

Key project deliverables:

 

 

Links to project page:

 

 

Evaluation:

 

https://unece.org/evaluation-reports
 
Part I. Planning
(to be filled in before submission to EXCOM)
Part II. Implementation
(to be used for reporting on progress in the implementation of the project in real time)1,2

Expected accomplishments

Planned activities

Estimated costs (US$)

 

Implemented activities3

Actual expenditures4 (US$)3

EA 1: Transparent dialogue between gas companies and UNECE member States. 

A1.1  Executive Board Meeting

30,000

Executive Board Meeting, January 2015 (Minutes, Programme 5th Forum)

20,928

A1.2  Meeting on supply, infrastructure and markets

52,500 11th Task Force Meeting on Supply, Infrastructure and Markets held in Aktau, KAZ, 26-27 Nov 2015 (Programme)    

A1.3 Gas Industry Forum

160,000 6th Gas Industry Forum held on 16 Dec 2015  (programme)    
 

A1.4 Meeting on Gas Markets and Regulation

105,332 5th Task Force Meeting on Gas Market and Regulation held in Brussels on 2 Dec 2015 (programme, minutes)  
Evaluation     Evaluation to be concluded by March 2017. 27,545

Total (incl. 13% Programme Support Costs)

  347,832    
Footnote


1 The secretariat shall inform EXCOM in case of unexpected developments or serious problems of any kind in the project implementation.
2 Questions from member States on project implementation will be forwarded to the secretariat.
Relevant information should be uploaded by the project manager on the Project Monitoring Tool within one month from the end of the activity and include the following:
(a) For an advisory service (including at a workshop/seminar/training organized by other organizations): title; venue; dates; project expenditures; and hyperlink(s) to presentation(s) and other relevant documents;
(b) For a workshop/conference/training organized by UNECE: title; venue; dates; project expenditures; and hyperlinks to the meeting agenda, list of participants, presentation(s) made by UNECE, conference documents, training materials and reports;
(c) For a consultancy: project expenditures; hyperlinks to the consultancy ToR and main outputs (study, report, training material, presentation, etc.) produced by the consultant/s;
(d) For other outputs not included under bullet points above: hyperlink to relevant documents.  
[1] Relevant financial information – certified by the Executive Office - should be uploaded by the project manager on the Project Monitoring Tool within one month from the end of the activity.