E240: Capacity-building for cooperation on dam safety in Central Asia (Phase 3)

 

EXCOM approval

Planning phase

Implementation phase

Final Reporting
and Evaluation phase

EXCOM form

Monitoring the Implementation

Substantive web page information for the project

 

Final/Terminal report

Evaluation ToR

Evaluation report

Implementation

 

 
Midpoint/Annual Progress Reports Annual funds utilization reports
Annual funds utilization report
 
Part I. Planning
(to be filled in before submission to EXCOM)
Part II. Implementation
(to be used for reporting on progress in the implementation of the project in real time)1,2

Expected accomplishments

Planned activities

Estimated costs (US$)

 

Implemented activities3

Actual expenditures4 (US$)3

EA 1: Improved inter-state cooperation and awareness on dam safety and related issues in Central Asia.

A1: Annual regional meetings for exchange of information and development of interstate cooperation (2 annual meetings and preparation of a joint publication).

 

 

104,000

1. Regional meeting 2013

2. Regional meeting 2014

3. Regional meeting 2015

 

 

 

 

 

 

EA 2: Improved national legislation and regulatory frameworks.    

A2: Support to development of national legislation and institutions (national seminars and provision of consultancy services in support of the development of national legislation and institutions).

 

80,000

1. Roundtable in Kazakhstan 2013

 

 

EA 3: Strengthened technical and legal capacity of experts and officials on dam safety issues.

A3: Organisation of an annual regional capacity building event "training the trainers", including the development of training material.  

54,000

1. Training courses 2013 and 2014

 

EA 4: Improved safety and transboundary cooperation on individual dams.

A4: Pilot activities on specific dams demonstrating technical solutions for transboundary safety monitoring (Development of safety monitoring and information exchange for the Ortotokoi dam).

62,000

1. Installation of Ortotokoi safety monitoring system
Total (including 13% of Programme Support Costs) 300,000 Total:  
Footnote


1 The secretariat shall inform EXCOM in case of unexpected developments or serious problems of any kind in the project implementation.
2 Questions from member States on project implementation will be forwarded to the secretariat.
Relevant information should be uploaded by the project manager on the Project Monitoring Tool within one month from the end of the activity and include the following:
(a) For an advisory service (including at a workshop/seminar/training organized by other organizations): title; venue; dates; project expenditures; and hyperlink(s) to presentation(s) and other relevant documents;
(b) For a workshop/conference/training organized by UNECE: title; venue; dates; project expenditures; and hyperlinks to the meeting agenda, list of participants, presentation(s) made by UNECE, conference documents, training materials and reports;
(c) For a consultancy: project expenditures; hyperlinks to the consultancy ToR and main outputs (study, report, training material, presentation, etc.) produced by the consultant/s;
(d) For other outputs not included under bullet points above: hyperlink to relevant documents.  
[1] Relevant financial information – certified by the Executive Office - should be uploaded by the project manager on the Project Monitoring Tool within one month from the end of the activity.