| Part I. Planning (to be filled in before submission to EXCOM |
Part II. Implementation (to be used for reporting on progress in the implementation of the project in real time) 1, 2 |
|||
|---|---|---|---|---|
| Expected accomplishments | Planned activities | Estimated costs (US$) |
Implemented activities (as of 31 July 2015) 3 | Actual expenditures4 (US$)3 |
| EA 1 Enhanced national policy formulation on population ageing and intergenerational and gender relations, to meet the challenges of demographic change |
A1.1 Policy Briefs on Ageing and in depth papers |
45,000 |
Publication: Intergenerational Family Relationships in Ageing Societies Background material for Policy Brief on: Innovative and empowering strategies for care Draft Policy Brief on: Dignity and non-discrimination for persons with dementia |
15,000 |
| A1.2 Road Maps on Ageing development and follow-up |
10,000 |
Publication: Road Map for mainstreaming ageing in Armenia |
6,000 | |
| A1.3 Capacity building/ training workshops and seminars |
20,000 |
Participation in the Working Group on Ageing meetings Workshop on Community Services for Elderly (Haifa, Israel - 2012) Workshop on ageing (Skopje, the Former Yugoslav Republic of Macedonia - 2012) First National Conference on Ageing (Moscow, Russia - 2013) |
7,500 | |
| A1.4 Knowledge base for policy action on ageing |
6,500 |
Experts participation in the Working Group on Ageing meetings Participation in international conferences related to ageing |
3000
|
|
| TOTAL | 81,500 | TOTAL | 31,500 | |
| NB: residual USD 50,000 transferred to E171 Ageing Phase II | ||||
Go back to the list of projects for Housing, Land Management and Population
1 The secretariat shall inform EXCOM in case of unexpected developments or serious problems of any kind in the project implementation.
2 Questions from member States on project implementation will be forwarded to the secretariat.
3 Relevant information should be uploaded by the project manager on the Project Monitoring Tool within one month from the end of the activity and include the following:
(a) For an advisory service (including at a workshop/seminar/training organized by other organizations): title; venue; dates; project expenditures; and hyperlink(s) to presentation(s) and other relevant documents;
(b) For a workshop/conference/training organized by UNECE: title; venue; dates; project expenditures; and hyperlinks to the meeting agenda, list of participants, presentation(s) made by UNECE, conference documents, training materials and reports;
(c) For a consultancy: project expenditures; hyperlinks to the consultancy ToR and main outputs (study, report, training material, presentation, etc.) produced by the consultant/s;
(d) For other outputs not included under bullet points above: hyperlink to relevant documents.
[1] Relevant financial information – certified by the Executive Office - should be uploaded by the project manager on the Project Monitoring Tool within one month from the end of the activity.